SYNERGY WAVE SYSTEM LLP achieved installing 300KWP capacity project at MUKESH GINNING MILLS, ADAMPUR MANDI, HISAR, HARYANA. After brainstorming through a wide range of options, we provided an optimum solution to MUKESH GINNING MILLS, HISAR, hence maximizing their ROI. A detailed case study follows below:
PROBLEM FACED BY THE CLIENT:
• Foremost issue faced by the client was high electricity bill and huge tariff from DISCOM
• Next in line was the space constraint
• They also failed at optimum generation due to major shed being non south facing
HOW DID SYNERGY RESOLVE THE SITUATION?
• We addressed their primary concern by installing SPP of 300KWP capacity & helped them save approximately 30 Lacs electricity bill annually
• MoNo half-cut 540WP were stationed to enhance space utilization
• We also installed MMS elevated were made south facing which maximized their solar generation capacity
Conclusion
MUKESH GINNING MILLS, HISAR were successful in achieving full capacity utilization and optimum generation of solar power by installing south facing MMS module by SYNERGY WAVE SYSTEM.